I'm trying to get several small maps set up with Acoustics data. With my current compute pool they each take 1-3 hours to do. After kicking off the bake for map #1, I can set up the probes & voxels for map #2, but the Bake tab shows "status: running: x/y tasks complete" for the map #1 job. The only option given is to cancel the bake in progress.

It would be great to have a "queue this bake to start when the current one finishes" option here, so the compute pool can get more work done overnight.

borogove avatar Jan 03 '20 01:01 borogove

Can you elaborate on what you'd envision the cache would do?

MikeChemi avatar Jan 03 '20 18:01 MikeChemi

Oh, sorry about that. I think I was misunderstanding something.

borogove avatar Jan 03 '20 18:01 borogove