pool-resource icon indicating copy to clipboard operation
pool-resource copied to clipboard

Claims environment but task never finishes

Open ameowlia opened this issue 8 years ago • 4 comments

This just started happening a lot on the Opsmanager pipeline.

It says it claims the environment, and the 2nd step of the job succeeds, but the 1st step of the job never stops running.

This build (below) has been running for 5 hours before we noticed it stuck on claiming the environment.

image

For our reference, if I want to look up this example again: https://om.ci.cf-app.com/teams/main/pipelines/opsmanager-1.8/jobs/openstack-clean-install-external/builds/24

ameowlia avatar Feb 27 '17 21:02 ameowlia

Hi there!

We use Pivotal Tracker to provide visibility into what our team is working on. A story for this issue has been automatically created.

The current status is as follows:

  • [ ] #140716827 Claims environment but task never finishes

This comment, as well as the labels on the issue, will be automatically updated as the status in Tracker changes.

concourse-bot avatar Feb 27 '17 21:02 concourse-bot

looks like something interrupted the progress of the build on the worker, so it re-started from scratch and tried acquiring again.

concourse version?

vito avatar Feb 28 '17 14:02 vito

concourse version: v2.6.0

We're still seeing this pretty regularly.

Here's another, slightly different, example.

image

  • the first half of the environment task never technically finished, even though the second half did, and even though it claimed an environment and moved on to the next step.

  • we decided to kill this job for unrelated reasons

  • the environment is never able to be released and we had an environment in limbo

ameowlia avatar Mar 08 '17 16:03 ameowlia

@ameowlia is this still happening? Did you upgraded your Concourse version in the meantime ?

marco-m avatar Oct 13 '18 07:10 marco-m